Hong Kong IPO disclosure precedents · 105 companies, 105 items
Disclosures of contract backlog/order reserve amounts and their growth or decline over the track record period, including drivers such as new order intake and expected recognition timing.
Uncompleted contract value increased to RMB2,006 million and success rate in tender bids
The table below sets forth the movement of our project backlog during the Track Record Period in terms of contract value and number of contracts:
Business · p. 133
We submitted 295, 329 and 245 tenders for the FY2023, FY2024 and FY2025, respectively, among which 45, 46 and 38 tenders were awarded to us, respectively, representing a tender success rate of approximately 15.3%, 14.0% and 14.7%, respectively. Our tender success rate remained stable during the Track Record Period.
Business · p. 144
During the Track Record Period, we had two early-terminated projects, which was primarily resulted from the changes in customer requirements or their operation conditions during the project implementation process.
54 design tender-winning projects secured, most of which have entered mass production
As of the Latest Practicable Date, we have secured 22 design-win projects from 14 commercial vehicle OEMs and tier-1 suppliers, with 13 projects already reaching mass production; we have also secured 32 design-win projects from 13 passenger vehicle OEMs and tier-1 suppliers, with 23 projects already reaching mass production.
Financial Information · p. 232
This has demonstrated our ability to continuously expand our customer base and generate recurring orders and stable revenue over the respective product life cycles of these projects.
Financial Information · p. 232
Based on our current business plan, order backlog, capacity utilization and cost structure, we expect to record net profit for the year ending December 31, 2026.
Changes in project backlog, ageing and successful tender rate
During FY2023, the backlog value decreased from RMB1,247.1 million to RMB995.6 million, due to the completion of a large number of projects which offset the newly awarded contracts.
Business · p. 160
During FY2025, the backlog value increased to RMB660.8 million, reflecting the increase in market demand from the aviation and aerospace sector which led to a significant in the number of newly secured contracts.
Business · p. 160
The tender success rate increased to 38.5% in FY2025 as a result of the improved alignment between submitted tenders and our expertise.
Sustained growth in the amount of pending contracts
As of March 31, 2026, we had a backlog of customer contracts valued at RMB501.6 million.
Business · p. 162
We have continued to scale our business, adding a new backlog of customer contracts valued at approximately RMB162.5 million during the period from January 1, 2026 and up to the Latest Practicable Date in 2026.
Summary · p. 14
(1) We expect to realize the revenue from the backlog as of December 31, 2025 in 2026 and 2027.
Changes in orders on hand and the value of newly signed contracts
In parallel, our new contract value (exclusive of VAT) increased from RMB448.8 million in 2023 to RMB759.4 million in 2025, reflecting robust demand for our solutions and strong commercial momentum.
Financial Information · p. 182
This growth in new contract value, coupled with a year-end backlog of RMB502.5 million as of December 31, 2025, provides meaningful visibility into our future revenue streams.
Financial Information · p. 182
Backlog might not be indicative of our future operating results and difficulties in contract performance could lead to inaccuracies with respect to the ultimate income from uncompleted contracts.
Orders of approximately RMB87.3 million secured in the fourth quarter of 2025
In particular, within Q4 2025, we secured multiple purchase orders of approximately RMB87.3 million for our Scale-up OCS solutions from (i) a major provider of communications equipment and ICT infrastructure in China, which includes about 8,200 Scale-up OCS modules and (ii) a developer of artificial intelligence computing chips, which includes about 2,000 Scale-up OCS modules.
Business · p. 187
Based on the current delivery and acceptance schedule, 56% of the total contract value (VAT excluded) was recognised as revenue in 2025, with the remaining 44% expected to be recognised as revenue in 2026.
Business · p. 187
Nonetheless, it is notable that certain letters of intent and framework agreements are legally non-binding in nature and do not constitute final agreements for the purchase of our products.
Value of customer contracts in hand of RMB440.5 million as at end of February 2026
As of February 28, 2026, we had 92 outstanding agreements with customers with an aggregate transaction value of RMB440.5 million, including 36 agreements for AI recognition business with a total transaction value of RMB159.1 million, 50 agreements for AI vertical industry application business with a total transaction value of RMB235.5 million, and 6 agreements for AI computing technical service business with a total transaction value of RMB46.0 million.
Summary · p. 11
We expect that among the total transaction value of RMB440.5 million outstanding agreements with customers, RMB375.9 million is expected to be paid by end of 2026, with the rest to be paid by the end of 2027.
Summary · p. 11
Our business growth continued after December 31, 2025.
Fluctuations in contract value of customisation projects (backlog), reaching RMB270.8 million at the end of 2025
Project backlog represents an estimate of the remaining aggregate contract sum of our customized sensor solution projects as at each of December 31, 2023, 2024 and 2025.
Business · p. 156
During the Track Record Period and up to the Latest Practicable Date, none of our backlog projects is cancelled or is expected to be cancelled.
Orders on hand and pipeline of new product development projects
As of February 28, 2026, our order backlog amounted to a total value in the hundreds of millions of RMB.
Financial Information · p. 211
As of December 31, 2025, we had 443 ongoing new product development projects with total expected annual revenue potential of over RMB1 billion.
Financial Information · p. 211
Among these projects, 84 have reached the business-win stage, having secured signed sales agreements and initial low-volume production orders, a stage critical for turning into mass production.
Orders on hand of approximately RMB496 million and loss-making projects
The year-on-year increase in the closing balance of contract value at the end of the year from 2023 to 2025 was primarily due to an increase in the volume of signed contracts driven by the continued business growth.
Business · p. 107
During the Track Record Period, there were nil, 2, and 8 loss-making projects in 2023, 2024, and 2025, respectively.
Business · p. 107
The total losses resulting from these projects were nil, RMB0.1 million, and RMB6.6 million in 2023, 2024, and 2025, respectively.
The Group expects to generate revenue from these projects in 2026 primarily from the supply of spare parts and/or the provision of technical service and/or O&M service.
Business · p. 173
For the Jinta 100MW Project, the remaining revenue to be recognized relates to spare parts supply which is expected to be completed by April 2026 and the provision of O&M service fees to be recognized over the five-year O&M period ending August 2030.
Over 2.4 million product purchase orders secured for 2026
As of the Latest Practicable Date, we secured over 2.4 million units in total purchase orders for 2026. Notably, over 25.0% of this volume, representing approximately RMB70.0 million, was contributed by customers other than Customer A.
Summary · p. 13
Our current and projected order volumes indicate continued revenue expansion in 2026 and beyond.
Orders in hand of approximately RMB171 million and NEV intended orders
As of January 31, 2026, we currently hold orders on hand totaling approximately RMB171.0 million, which comprises approximately RMB46.1 million supported by confirmed customer orders and approximately RMB124.9 million supported by potential customer demand.
Business · p. 179
Furthermore, we have secured aggregate indicative orders of RMB37.2 million from this customer, which are expected to be formally placed progressively in early 2026 based on the customer’s production schedule, with corresponding revenue recognition anticipated within 2026.
Business · p. 179
However, based on gross profit margins of comparable products in the industry, such as the 36.1% comprehensive gross margin reported by our competitor in China and the 50%−60% gross margin for analog chips reported by our other global competitor, we anticipate achieving a gross profit margin in the range of 35% to 40% for these products.
Orders in hand of robots and systems of approximately RMB2.2 billion as at end of 2025
As of December 31, 2025, we have achieved an aggregate backlog value of robots and systems of approximately RMB2.2 billion, which we expect to fulfill within the next three years.
Business · p. 125
Specifically, approximately 44.7% of the backlog is expected to be fulfilled in 2026, and 47.3% in 2027, with the remaining balance expected to be fulfilled in 2028.
Business · p. 125
As of December 31, 2025, we have achieved an aggregate backlog value of robots and systems of approximately RMB2.2 billion, out of which 46 were ongoing overseas projects with an aggregate backlog of RMB685.0 million.
Total amount of orders in hand decreased from RMB52.7 million to RMB2.7 million
As at 31 December 2023, 31 December 2024 and 31 December 2025, we had a total of 12, 19 and 8 projects in our backlog (including projects that have commenced but not completed as well as projects that have been awarded to us but not yet commenced) with revenue derived or expected to be derived from such projects as follows:
Orders with revenue pending recognition of RMB26.1 million, up 163.1% year on year
As of January 31, 2026, the total value of our confirmed orders pending revenue recognition was RMB26.1 million, representing a 163.1% increase compared to January 31, 2025.
Summary · p. 19
Subsequent to the Track Record Period and up to the Latest Practicable Date, our business operations had remained stable.
Total value of orders in hand of approximately RMB95.8 million
As of September 6, 2025, we had an aggregate order value of approximately RMB95.8 million to be fulfilled. We expect to deliver products to our customers under these orders in around two months.
Business · p. 225
Our average order-to-revenue cycle is one to two months, which is relatively short and consistent with industry practice as advised by CIC.
Contracted sales volume of 61 units of core product, subsequently increased to 118 units
in terms of contractual sales volume, we have entered into agreements for sales of 61 units of our Core Products globally as of June 30, 2025.
Summary · p. 7
In terms of contractual sales volume, we have entered into agreements for sales of 31 units of Edge Multi-Port Endoscopic Surgical Robot in the six months ended June 30, 2025.
Summary · p. 2
In terms of contractual sales volume, we have entered into agreements for sales of 118 units of our Core Products globally as of the Latest Practicable Date, including 46 units in China and 72 units in overseas countries.
Unfulfilled binding orders of approximately RMB821.8 million
As of the Latest Practicable Date, we had 24 unfulfilled binding orders for our Specialist Technology Product with a total value of approximately RMB821.8 million.
Summary · p. 4
In addition, as of the Latest Practicable Date, we have entered into five framework sales agreements and 24 sales contracts for our Specialist Technology Product with a total value of approximately RMB1,240.7 million, which will contribute to our future revenue when realized.