Total contract value of orders on hand of RMB1,329.6 million
As of the Latest Practicable Date, our order backlog had a total contract value of RMB1,329.6 million, which is expected to be recognized by December 31, 2026.
Uncompleted contract value increased to RMB2,006 million and success rate in tender bids
The table below sets forth the movement of our project backlog during the Track Record Period in terms of contract value and number of contracts:
Business · p. 133
We submitted 295, 329 and 245 tenders for the FY2023, FY2024 and FY2025, respectively, among which 45, 46 and 38 tenders were awarded to us, respectively, representing a tender success rate of approximately 15.3%, 14.0% and 14.7%, respectively. Our tender success rate remained stable during the Track Record Period.
Business · p. 144
During the Track Record Period, we had two early-terminated projects, which was primarily resulted from the changes in customer requirements or their operation conditions during the project implementation process.
54 design tender-winning projects secured, most of which have entered mass production
As of the Latest Practicable Date, we have secured 22 design-win projects from 14 commercial vehicle OEMs and tier-1 suppliers, with 13 projects already reaching mass production; we have also secured 32 design-win projects from 13 passenger vehicle OEMs and tier-1 suppliers, with 23 projects already reaching mass production.
Financial Information · p. 232
This has demonstrated our ability to continuously expand our customer base and generate recurring orders and stable revenue over the respective product life cycles of these projects.
Financial Information · p. 232
Based on our current business plan, order backlog, capacity utilization and cost structure, we expect to record net profit for the year ending December 31, 2026.
Changes in project backlog, ageing and successful tender rate
During FY2023, the backlog value decreased from RMB1,247.1 million to RMB995.6 million, due to the completion of a large number of projects which offset the newly awarded contracts.
Business · p. 160
During FY2025, the backlog value increased to RMB660.8 million, reflecting the increase in market demand from the aviation and aerospace sector which led to a significant in the number of newly secured contracts.
Business · p. 160
The tender success rate increased to 38.5% in FY2025 as a result of the improved alignment between submitted tenders and our expertise.
During the Track Record Period, some of our intelligent energy operation and management projects and intelligent energy efficiency projects were secured by tender or quotations.
Business · p. 134
Number of projects for which we submitted a tender | 42 | 57 | 63
Business · p. 134
We were awarded and entered into 42, 57 and 63 contracts in 2023, 2024 and 2025, respectively.
Identification of three loss-making energy operation and management projects and impairment provision
For our intelligent energy operation and management projects, if the recoverable revenue over a project’s entire lifecycle is expected to be insufficient to cover both incurred and perspective costs, we will identify it as a loss-making project after conducting a comprehensive assessment.
Business · p. 116
During the Track Record Period, we identified three intelligent energy operation and management projects as loss-making and therefore we made sufficient impairment provisions.
Business · p. 116
The losses recognized for these projects are immaterial and do not have a material adverse impact on the overall operations, financial performance and profitability of our Group.
Sustained growth in the amount of pending contracts
As of March 31, 2026, we had a backlog of customer contracts valued at RMB501.6 million.
Business · p. 162
We have continued to scale our business, adding a new backlog of customer contracts valued at approximately RMB162.5 million during the period from January 1, 2026 and up to the Latest Practicable Date in 2026.
Summary · p. 14
(1) We expect to realize the revenue from the backlog as of December 31, 2025 in 2026 and 2027.
Changes in orders on hand and the value of newly signed contracts
In parallel, our new contract value (exclusive of VAT) increased from RMB448.8 million in 2023 to RMB759.4 million in 2025, reflecting robust demand for our solutions and strong commercial momentum.
Financial Information · p. 182
This growth in new contract value, coupled with a year-end backlog of RMB502.5 million as of December 31, 2025, provides meaningful visibility into our future revenue streams.
Financial Information · p. 182
Backlog might not be indicative of our future operating results and difficulties in contract performance could lead to inaccuracies with respect to the ultimate income from uncompleted contracts.
Three loss-making projects during the Track Record Period
During the Track Record Period, we had three loss-making projects, with aggregated gross loss of RMB4.9 million.
Business · p. 134
Our Directors consider that the losses recognized as a result of these loss-making projects were acceptable losses that may arise out of our ordinary course of business and such losses were insignificant to our operations, financial performance and profitability as a whole.
Three major loss-making projects in the new energy investment and development business
During the Track Record Period, we had three major loss-making new energy investment and development projects.
Business · p. 172
During the Track Record Period, the total revenue and gross loss from these projects were RMB1,230.8 million and RMB81.0 million, respectively.
Business · p. 172
These losses were primarily due to (i) the relatively low project selling price, impacted by the declined market electricity prices; and (ii) the increased construction costs, resulting from project delays caused by the public health incidents.
Fluctuation in projects in hand and bid-winning rate
The following table summarizes certain details of our revenue-generating projects of our core business lines, including the movement of projects on hand, tender success rate, contract value and revenue, for the periods indicated.
Orders of approximately RMB87.3 million secured in the fourth quarter of 2025
In particular, within Q4 2025, we secured multiple purchase orders of approximately RMB87.3 million for our Scale-up OCS solutions from (i) a major provider of communications equipment and ICT infrastructure in China, which includes about 8,200 Scale-up OCS modules and (ii) a developer of artificial intelligence computing chips, which includes about 2,000 Scale-up OCS modules.
Business · p. 187
Based on the current delivery and acceptance schedule, 56% of the total contract value (VAT excluded) was recognised as revenue in 2025, with the remaining 44% expected to be recognised as revenue in 2026.
Business · p. 187
Nonetheless, it is notable that certain letters of intent and framework agreements are legally non-binding in nature and do not constitute final agreements for the purchase of our products.
For certain sales, such as sales to automotive manufacturers and sales of smart laboratory equipment and software, there is normally a tender process where we are required to submit tender with design proposals for some of our customers' new projects.
Business · p. 137
We had a sustainable tender success rate at 26.7%, 25.4% and 31.2% for FY2023, FY2024 and FY2025, respectively, and we believe that demonstrates our capability to capture new projects and business opportunities.
Value of customer contracts in hand of RMB440.5 million as at end of February 2026
As of February 28, 2026, we had 92 outstanding agreements with customers with an aggregate transaction value of RMB440.5 million, including 36 agreements for AI recognition business with a total transaction value of RMB159.1 million, 50 agreements for AI vertical industry application business with a total transaction value of RMB235.5 million, and 6 agreements for AI computing technical service business with a total transaction value of RMB46.0 million.
Summary · p. 11
We expect that among the total transaction value of RMB440.5 million outstanding agreements with customers, RMB375.9 million is expected to be paid by end of 2026, with the rest to be paid by the end of 2027.
Summary · p. 11
Our business growth continued after December 31, 2025.
Fluctuations in contract value of customisation projects (backlog), reaching RMB270.8 million at the end of 2025
Project backlog represents an estimate of the remaining aggregate contract sum of our customized sensor solution projects as at each of December 31, 2023, 2024 and 2025.
Business · p. 156
During the Track Record Period and up to the Latest Practicable Date, none of our backlog projects is cancelled or is expected to be cancelled.
Loss-making projects resulting in an annual loss of up to RMB16.4 million
For each year during the Track Record Period, we recorded seven, six and four loss-making projects, incurring a total loss of approximately RMB2.9 million, RMB16.4 million and RMB6.3 million for the corresponding year.
Business · p. 157
The losses incurred from the loss-making projects were primarily attributable to underestimation of project costs.
Orders on hand and pipeline of new product development projects
As of February 28, 2026, our order backlog amounted to a total value in the hundreds of millions of RMB.
Financial Information · p. 211
As of December 31, 2025, we had 443 ongoing new product development projects with total expected annual revenue potential of over RMB1 billion.
Financial Information · p. 211
Among these projects, 84 have reached the business-win stage, having secured signed sales agreements and initial low-volume production orders, a stage critical for turning into mass production.
Orders on hand of approximately RMB496 million and loss-making projects
The year-on-year increase in the closing balance of contract value at the end of the year from 2023 to 2025 was primarily due to an increase in the volume of signed contracts driven by the continued business growth.
Business · p. 107
During the Track Record Period, there were nil, 2, and 8 loss-making projects in 2023, 2024, and 2025, respectively.
Business · p. 107
The total losses resulting from these projects were nil, RMB0.1 million, and RMB6.6 million in 2023, 2024, and 2025, respectively.
Success rate of bids and quotations ranged between 36.7% and 50.4%
In 2023, 2024 and 2025, we submitted 117, 90 and 53 tenders and quotations and were awarded 59, 33 and 25 projects, respectively.
Our overall success rate for the tenders and quotations submitted was approximately 50.4%, 36.7% and 47.2% in 2023, 2024 and 2025, respectively.
In January 2026, we won a tender of a food waste treatment project in Jinzhou city, Liaoning province with a contract price of RMB71.5 million for construction of the project.