Ownership certificates obtained for all owned properties
As advised by our PRC Legal Advisers, we have obtained the land use right certificates and building ownership certificates for all our owned properties since our commencement.
Title to owned land and properties confirmed to be legal and valid
As of the Latest Practicable Date, our PRC Legal Advisors confirmed that we legally and validly owned the rights to use the aforementioned land parcels, with no existing ownership disputes.
Business · p. 250
As confirmed by our PRC Legal Advisors, we legally and validly own the aforementioned properties, with no existing ownership disputes.
Certain self-owned properties have not obtained house ownership certificate
As of the Latest Practicable Date, we do not have the title certificate for one of our owned properties used as for parcel delivery and guardhouse, totaling 38.7 sq.m.
Risk Factors · p. 51
The authority further confirmed it will not require the demolition of the delivery and guardhouse, and the absence of a property ownership certificate for the delivery and guardhouse does not constitute a material violation and will not result in administrative penalties by the authority
Business · p. 207
our PRC Legal Advisor is of the view that the risk of penalty arising from the absence of property ownership certificate is low and such non-compliance is not expected to have any material adverse effect on the business operations of our Company or our PRC subsidiaries.
Termination of factory construction and suspension in compliance with laws and regulations
As advised by our PRC Legal Advisors, we had complied with applicable laws, regulations and contractual obligations in all material respects in relation to the termination of Zhenjiang factory construction, as well as the deferred construction of the Chaoyang and Jinchang factories as of the Latest Practicable Date.
Ownership certificates obtained for owned properties and uses are in compliance
As advised by our PRC Legal Advisor, our Group has obtained ownership certificates and our use of the properties does not contravene the use specified in the ownership certificates with respect to the properties we owned.
Business · p. 159
As of June 30, 2026, we owned fourteen properties in the PRC with an aggregate GFA of approximately 247,825.5 sq.m., primarily used for production, R&D, offices and warehousing purposes.
Certain self-owned properties have not obtained house ownership certificates
We remain in the process of preparing the application for the relevant ownership certificates and expect to complete the relevant procedures by the end of 2026.
Business · p. 177
As of June 30, 2026, the aggregate gross floor area of properties owned by us and our major subsidiaries lacking ownership certificates accounted for 1.0% of the total gross floor area of properties owned by us and our major subsidiaries in the Chinese mainland.
Nine owned properties without real estate ownership certificates
As at the Latest Practicable Date, due to historical legacy construction projects executed on the underlying parcels of government allocated and collective land authorised by the local government authority, we have not obtained valid real estate ownership certificates for nine owned properties, of which Beijing Sinder (as our wholly-owned subsidiary) have used for storage and warehousing facilities and utilities with an aggregate floor area of approximately 1,355.0 sq.m.
Business · p. 152
However, given that (i) the aforementioned properties without valid real estate ownership certificates represent only approximately 1.32% of the aggregate GFA; (ii) the properties occupied by Beijing Sinder without valid property ownership certificates are used mainly for non-core functions such as warehousing and generator rooms which would not affect key production facilities and result in material operational impact; (iii) Beijing Sinder has obtained compliance certificates from relevant government authorities confirming that there were no violations of laws and regulations were recorded in the housing and urban-rural construction sector covering the Track Record Period; and (iv) there was no major disputes or conflicts of us using the subject land, our PRC Legal Adviser is of the view that the absence of real estate ownership certificate for the aforementioned properties will not have any material adverse effect on our Group’s ability to continue operations.
Business · p. 152
As at the Latest Practicable Date, our Group is in the course of obtaining registration certificates for the nine owned properties with title defects.
Inability to obtain title certificates for self-owned wharf properties in the Slender West Lake Scenic Area
As of the Latest Practicable Date, we were not allowed and unable to obtain the land use rights for the aforementioned properties, and local regulations prohibit the issuance of property ownership certificates for structures such as wharves and ancillary facilities within the Slender West Lake Scenic Area.
Business · p. 171
According to the confirmation letter issued by the Shugang-Slender West Lake Administrative Committee in January 2026, it is agreed that our Company could lease such ancillary facilities to third parties and has an exclusive right to the income generated from such lease(s); and it is further explicitly confirmed that there is no ownership dispute over the ancillary facilities constructed by our Company.
Ownership certificates for owned land and properties complete
During the Track Record Period and up to the Latest Practicable Date, we had obtained the building ownership certificates for all of our owned properties in China.
Business · p. 162
As of the Latest Practicable Date, our rights to use such lands were lawful and valid, and there were no disputes or potential disputes over the ownership of such lands.
Three owned production properties without ownership certificates
As of June 30, 2026, for three properties we used as production facilities in China, we were not able to obtain the required ownership related certificate from the local government authorities.
Risk Factors · p. 51
Considering the cumulative book value of these properties is less than 1% of the total book value of our owned properties and that these properties primarily serve as auxiliary production facilities, the risk of any material adverse effect on our business, results of operations or financial condition is remote.
Land use right certificates obtained for owned land
Our PRC Legal Adviser confirmed that, as of the Latest Practicable Date, we had obtained all relevant land use rights certificates for this property in China.
Certain of our own land and buildings have not obtained title certificates
We have not obtained valid land use rights certificates, building ownership certificates or other required approvals for certain of these properties.
Risk Factors · p. 54
As of the Latest Practicable Date, our Group was using but had not obtained title certificates for parcels of land with an aggregate area of approximately 3,159,373.4 sq.m., comprising:
Business · p. 143
As of the Latest Practicable Date, our Group was using but had not obtained building ownership certificates for buildings with an aggregate GFA of approximately 9,619.6 sq.m., comprising:
Three ancillary buildings at Kunshan production base without completed construction approval and property ownership certificates
We constructed three ancillary structures at our Kunshan production base, comprising two water-recycling equipment rooms as well as an air-compressor equipment and power-distribution equipment room, with an aggregate gross floor area of approximately 2,087 square meters (the “Relevant Structures”), without completing the applicable environmental impact assessment, construction project planning, construction permit and other approval procedures. Accordingly, we have not obtained real estate ownership certificates for the Relevant Structures.
Risk Factors · p. 34
our Directors and our PRC Legal Advisor are of the view that the lack of real estate ownership certificates for the Relevant Structures will not have a material adverse effect on our Group’s overall production and business operations.
Risk Factors · p. 34
On May 11, 2023, the Comprehensive Administrative Enforcement Bureau of the Kunshan Economic and Technological Development Zone agreed in writing that demolition of the relevant equipment rooms could be deferred.
RA Chemical's production line put into use without acceptance inspection
During the Track Record Period, the production lines of rubber resins and additives and PBAT of the RA Chemical factory had been in use prior to obtaining the required acceptance of completed construction project.
Business · p. 143
Based on the total contract price of the relevant buildings, the maximum potential fines in respect of the above non-compliances are estimated to be approximately RMB7.3 million.
Business · p. 143
As at the Latest Practicable Date, we had obtained the relevant acceptance of completed construction project and building ownership certificate for the properties of RA Chemical.
Certain self-owned buildings of RA Zhenjiang without property ownership certificates
As at 30 June 2026, we owned a total of 32 properties within the PRC and we have obtained property ownership certificates and/or building ownership certificates for our owned properties, except that RA Zhenjiang had not obtained the relevant building ownership certificate in respect of buildings with a total gross floor area of approximate 9,321.68 sq.m..
Business · p. 143
As advised by our PRC Legal Adviser, the lack of building ownership certificates does not affect our normal use of the properties or subject us to any administrative penalty under applicable PRC laws and regulations, but it may affect the exercise of our rights in the transfer, mortgage or disposal of the underlying properties.
Construction permits and filings for certain construction works not obtained in a timely manner
During the Track Record Period, we did not obtain construction permits or make required filings for certain construction and renovation projects in a timely manner, with a project contract value of RMB1.3 million, primarily due to inadvertent oversight and unfamiliarity with evolving regulatory requirements which prevented timely completion of the necessary application.
Business · p. 192
The potential maximum penalty in respect of fines that we may be exposed to due to the lack of construction permits or filings amounted to approximately RMB27 thousand.
Property acquired by RA Zhenjiang lacks planning and construction permits
During the Track Record Period, we had not obtained the requisite construction planning permit (建設工程規劃許可證), construction commencement permit (施工許可證) and/or acceptance of completed construction project prior to the commencement of construction and/or operations of certain production facilities, which may subject us to administrative penalties under the applicable PRC laws and regulations.
Risk Factors · p. 39
Due to the lack of relevant records, we were unable to ascertain whether the Pre-acquisition Properties had obtained the relevant construction planning permit and construction commencement permit prior to their construction.
Business · p. 144
our PRC Legal Adviser is of the view that, barring any material change in the PRC policies and regulations and the implementation and regulatory requirements of the local governments, the risk that the relevant government authority would impose administrative penalties on RA Zhenjiang with respect to the above non-compliances is remote, and such non-compliance incidents would not have any material adverse effect on the normal use and operation of the properties of RA Zhenjiang.
Buildings used without acceptance inspection after acquisition by RA Zhenjiang
In addition, the remaining buildings with approximately 1,435.96 sq.m. that were constructed after our acquisition of RA Zhenjiang had been in use prior to obtaining the required acceptance of completed construction project ("Post-acquisition Properties").
Business · p. 144
As at the Latest Practicable Date, we have obtained the building ownership certificate in respect of the Post-acquisition Properties.
Twelve self-owned buildings have not obtained building ownership certificates
As of the Latest Practicable Date, our Group had not obtained the building ownership certificates for 12 of our owned buildings, which are all based on our self-owned land, with an aggregated gross floor area of approximately 182,436 sq.m. in the PRC.
Business · p. 166
In addition, as of the Latest Practicable Date, we had not obtained the real property ownership certificates for 12 properties occupied by us, with an aggregate gross floor area of approximately 182,436 sq.m.
Risk Factors · p. 46
Subject to the review and approval procedures of the competent authorities, we expect to complete the rectification procedures and obtain the building ownership certificates for the remaining ten buildings by December 31, 2027.