Put into use before completion acceptance

Hong Kong IPO disclosure precedents · 1 companies, 2 items

Production lines, plants or buildings put into use before obtaining completion acceptance (竣工验收), with quantified potential fines and remediation such as later obtaining acceptance and credit reports.

Compliance matters are read from filings since 24 August 2026.

2026-09-21ProspectusNon-compliance
Red Avenue New Materials Group Co., Ltd.彤程新材料集团股份有限公司09607.HK

During the Track Record Period, the production lines of rubber resins and additives and PBAT of the RA Chemical factory had been in use prior to obtaining the required acceptance of completed construction project.

Business · p. 143

Based on the total contract price of the relevant buildings, the maximum potential fines in respect of the above non-compliances are estimated to be approximately RMB7.3 million.

Business · p. 143

As at the Latest Practicable Date, we had obtained the relevant acceptance of completed construction project and building ownership certificate for the properties of RA Chemical.

Business · p. 143
The company's explanation, the adviser's view and the page in the filing: see Matters
2026-09-21ProspectusNon-compliance
Red Avenue New Materials Group Co., Ltd.彤程新材料集团股份有限公司09607.HK

In addition, the remaining buildings with approximately 1,435.96 sq.m. that were constructed after our acquisition of RA Zhenjiang had been in use prior to obtaining the required acceptance of completed construction project ("Post-acquisition Properties").

Business · p. 144

As at the Latest Practicable Date, we have obtained the building ownership certificate in respect of the Post-acquisition Properties.

Business · p. 144
The company's explanation, the adviser's view and the page in the filing: see Matters