深圳市远信储能技术股份有限公司RelyEZ Energy Storage Technology Co., Ltd.09621.HK
嵩明项目终止及1.721亿元成品重新调配
Due to the compressed project timetable, we began production for the Songming project in advance in April 2025. As a result, finished goods of RMB172.1 million were produced for the project.
Business · 第 169 页
Our commencement of production without receipt of the advance payment and the delivery-linked installment payment represented a deviation from our normal commercial practice.
Business · 第 170 页
As the project was not further pursued, we recognized inventory impairment of RMB2.1 million in 2025 in respect of the finished goods produced for the Songming project, and we did not receive any compensation from Songming Lingwei.
To the best knowledge of our Directors, among the contracts newly entered in 2024, 49 projects experienced delays, representing approximately 7.0% of the total number of contracts; in terms of the contract value, the delayed projects accounted for approximately 30.1% of the total contract value newly signed in 2024.
Business · 第 130 页
Among the 49 delayed projects identified for 2024, all commenced revenue recognition in 2025 and substantially all of the corresponding revenue had been recognized as of July 31, 2026; further, as of July 31, 2026, approximately 78.8% of the corresponding trade receivables had been collected.
The delay was primarily because: (i) our client's customs clearance delays impeded the timely entry of the PS building components manufactured by us; and (ii) the rainy season in Thailand rendered the site unsuitable for construction activities from June to late October in 2024.
Business · 第 226 页
During the Track Record Period, for projects where delays resulted in significant additional costs, we received sufficient compensation from our customers.
Business · 第 227 页
Save for disclosed above, none of the construction projects carried out by us experienced material delays, project cancellation, cost overruns and loss-making during the Track Record Period and up to the Latest Practicable Date.
云知声智能科技股份有限公司UNISOUND AI TECHNOLOGY CO., LTD.09678.HK
世茂集团项目积压及实施进度延后
As of December 31, 2024, the total revenue recognized from these projects amounted to RMB219.9 million, and as of the same date, the total backlog contract value of these projects amounted to RMB44.2 million.
Business · 第 230 页
They have not yet been implemented, and no costs have been incurred, due to the delays in the associated civil/commercial property construction.
Business · 第 231 页
We have not recognized any revenue for a few contracts with Shimao Group that had commenced for more than a year, totaling RMB6.7 million as of April 30, 2025, due to the overall schedule adjustment of the construction projects, which in turn affected our implementation of AI solutions.
江苏国富氢能技术装备股份有限公司Jiangsu Guofu Hydrogen Energy Equipment Co., Ltd.02582.HK
齐鲁氢能一体化项目交付延迟
However, due to the impact of COVID-19, the construction of Phase I of the Integration Project was delayed.
Business · 第 307 页
In light of the above, and through discussion with Qilu Hydrogen, it was mutually agreed by both parties that the delivery of the relevant equipment for hydrogen liquefaction and the storage and transportation of liquid hydrogen to Qilu Hydrogen would be delayed.
Business · 第 308 页
We delivered the relevant products to Qilu Hydrogen by batches starting from April to December 2023, and Qilu Hydrogen has confirmed its acceptance of our products.
By mid-2020, we were informed that our works schedule of Project No. #02 would be revised primarily due to changes in design and drawings of structural steelwork by the project owner and that the substantial part of our construction site works would be rescheduled to 2021.
Summary · 第 3 页
Later in mid-2021, our Group was informed that the substantial part of our construction site works under Project No. #02 would be further rescheduled due to the late handover of the relevant work sites to us.
Summary · 第 3 页
Pursuant to the contract terms of the service agreement for Project No. #02, in the event our contract works under Project No. #02 was not completed within the original schedule due to reason(s) other than our default, our Group shall be entitled to apply in writing to Hip Hing Group for an extension to project duration and claim for any additional costs reasonably incurred by us arising from the delay.
升辉清洁集团控股有限公司Shenghui Cleanness Group Holdings Limited02521.HK
部分项目提前终止致收入损失
Our number of projects which was subject to early termination during the Track Record Period was 2, 1, 7 and nil, respectively, amounting to a loss of revenue of approximately RMB1,174,000, RMB10,000, RMB2,038,000 and nil, respectively.
Business · 第 183 页
As confirmed by our Directors, these circumstances was mainly due to the fact that (i) our customers ended their agreements (for example, lease agreements) with related parties (for example, landlords or property management companies); and (ii) the service scope for renewed projects granted by the tender offerors have been reduced/modified.
山西省安装集团股份有限公司Shanxi Installation Group Co., Ltd.02520.HK
手头订单项目取消及延迟
For the years ended December 31, 2020, 2021 and 2022, the six months ended June 30, 2023 and from July 1 2023 to the Latest Practicable Date, the Group had 22, nil, 11, eight and six projects cancelled, which were mainly due to external factors, such as the lack of funding on the part of the customers or investors or the change in design subsequent to the entering into of the contracts.
Summary · 第 3 页
Furthermore, the Group had 13 projects, with an aggregate contract value of RMB1,937.2 million, which had experienced delay (i.e. delay of more than 12 months from the original completion date as stated in the original contract) during the Track Record Period.
Business · 第 224 页
Our bidding success rate, which ranged between 47.0% and 57.7%, did not fluctuate materially during the Track Record Period.
The outbreak of COVID-19 reduced the number and availability of patients with relapsed/refractory B cell non-Hodkin's lymphoma who could commit to the 28 consecutive days of hospitalization and treatment of K193 for the Phase I clinical trial, which caused a temporary delay in subject enrollment.
Business · 第 282 页
As of the Latest Practicable Date, we had enrolled 17 subjects and were in the dose escalation stage for this trial, but no safety or tolerability data is currently available.
Business · 第 282 页
However, the Phase I clinical trial for K11 was suspended because we were only able to recruit 58 subjects and unable to complete enrollment of the planned number of 96 subjects, which is not within our control and is not related to the product quality of K11.